Beginning in the middle of last month our team began work on a water project for the community of Semesche. We had been working for quite some time on the Semesche project, actually all the way back to February of this year. Through various answered prayers and much time spent walking with the community, we finally arrived at a point to start construction. Below are two pictures taken of the spring before any construction began.
During past water projects, all the construction work (concrete and pipe) had been done during a visiting team from the U.S. This time around we decided to change our project management methods a bit and attempt to have all the "gray construction" done before a team arrived. Below are a few pictures of some of the "gray construction".
Excavation of the spring site.
Forming up the Spring Box
Finished spring box.
Tank site.
Finished tank, two sides holding about 3000L each.
We also had all our PVC materiales ordered well before the team arrived to make sure we had everything needed. This is a picture of our storage building for all the PVC parts.
Another thing we have been focusing on doing better of is training our local team. This is a picture of our local Water Tech Julio, giving a presentation to the visiting team on the Semesche Project Design. Julio talked through all the main principle lines, service lines and valved boxes. It was an amazing experience to watch and participate in this process with Julio.
On Friday the team was scheduled to arrive in Coban and then travel to Semesche on Saturday to begin putting pipe in the ground. Before leaving to head out to meet the team in Coban on Friday, I walked the system with the guys from the community. By Friday at noon, we had just finished walking the line and no trench had been dug. We had over 2km of pipe to get in the ground in 4 days, and it would be pretty tough to do this without trench. By the time we arrived in Semesche around noon on Saturday with the visiting team, 91 men from the community had already dug over 1km of line... extremely impressive! Pictured below is 2" principle line waiting to be glued and laid in the trench.
Mark is pictured opening up the cleaning valve at the lowest point in the system while we were testing the water pressure on Tuesday. An amazing amount of water!!
Here is water coming out of the spigot by the Semesche school.
Thanks the the KnoxProCorp team of December 2012 for helping us make the Semesche project a reality!!